S-39 · Work orders
Awarded work orders
Mobilisation advance recovery and physical progress against issued WOs.
Live WOs
2
in execution
Value running
₹57.5 Cr
Terminated
1
default / cure-period lapsed
Avg progress
62%
| WO | Vendor | Scope | Value ₹Cr | Issued | Mob adv % | % done | Status |
|---|---|---|---|---|---|---|---|
| WO-2026-014 | L&T Construction | MHADA Goregaon Ph-3 · MEP | 38.4 | 2026-04-12 | 10 | 38% | running |
| WO-2025-097 | Shapoorji & Sons | Dharavi Cluster 4 · earthworks | 19.1 | 2025-11-02 | 10 | 82% | running |
| WO-2024-031 | Afcons Infra | Mulund tower A · structure | 62.0 | 2024-08-19 | 10 | 100% | completed |
| WO-2025-046 | Globex Constructions | Bhandup BLC pkg | 9.4 | 2025-06-30 | 10 | 28% | terminated |