S-39 · Work orders

Awarded work orders

Mobilisation advance recovery and physical progress against issued WOs.

Live WOs
2
in execution
Value running
₹57.5 Cr
Terminated
1
default / cure-period lapsed
Avg progress
62%
WOVendorScopeValue ₹CrIssuedMob adv %% doneStatus
WO-2026-014L&T ConstructionMHADA Goregaon Ph-3 · MEP38.42026-04-121038%running
WO-2025-097Shapoorji & SonsDharavi Cluster 4 · earthworks19.12025-11-021082%running
WO-2024-031Afcons InfraMulund tower A · structure62.02024-08-1910100%completed
WO-2025-046Globex ConstructionsBhandup BLC pkg9.42025-06-301028%terminated