M6.2 · Construction & delivery

Construction watch

Physical vs financial drawdown · contractor league · geo-tagged photo evidence wall.

ScopeMinister of State (Housing)·State — exception view

Schemes (14)

financial > physical + 10% → amber flag
CIDCO · Taloja
Taloja Greens
1,640 units · 8 towers · P52000033109
AHPDelayed 90+ daysOC pending
Physical71%
Financial70%
CIDCO · Panvel
Panvel East Affordable
980 units · 5 towers · P52000034220
AHPDelayed 90+ daysOC pending
Physical64%
Financial60%
CIDCO · Dronagiri
Dronagiri Port Quarters
600 units · 3 towers · P52000036114
ISSDelayed 90+ daysOC pending
Physical52%
Financial55%
MHADA · Konkan
Konkan Ridge Co-op
1,080 units · 5 towers · P51700029884
AHPDelayed 90+ daysOC pending
Physical72%
Financial84%
⚠ Financial ahead of physical by 12%
MHADA · Pune
Pune Mission Affordable
1,480 units · 7 towers · P52100020112
BLCDelayed 90+ daysOC pending
Physical65%
Financial68%
Maha Housing · State JV
Aurangabad TOD Township
2,120 units · 9 towers · P53000018330
AHPDelayed 90+ daysOC pending
Physical58%
Financial61%
SRA · Mumbai Slum
Dharavi Rehab Cluster 4
2,480 units · 12 towers · P51900014772
BLCDelayed 90+ daysOC pending
Physical41%
Financial44%
SRA · Mumbai Slum
Bandra Reclamation Rehab
1,640 units · 8 towers · P51900015220
BLCDelayed 90+ daysOC pending
Physical36%
Financial46%
CIDCO · Ulwe
Ulwe Pearl Phase II
1,240 units · 6 towers · P52000035821
ISS
Physical86%
Financial83%
CIDCO · Kharghar
Kharghar Sky Towers
820 units · 4 towers · P52000031244
ISS
Physical94%
Financial91%
MHADA · Nashik
Nashik Valley Homes
760 units · 4 towers · P51900022014
AHP
Physical78%
Financial75%
MHADA · Nagpur
Nagpur Metro Quarters
1,180 units · 6 towers · P51800024417
ISS
Physical81%
Financial92%
⚠ Financial ahead of physical by 11%
MHADA · Mumbai
Worli Worker Housing
540 units · 3 towers · P51700030001
AHP
Physical92%
Financial96%
MHADA · Mumbai
Ghatkopar Transit Camp
360 units · 2 towers · P51700030218
AHP
Physical98%
Financial94%

S-37 · Contractor league table

on-time · cost variance · safety
ContractorSchemesUnitsOn-timeCost ΔSafety
Shapoorji Pallonji E&C65,84092%-1.2%A
L&T Construction · BBE44,12088%+0.8%A
Tata Projects · UB32,98081%+2.1%B
Capacite Infraprojects54,46074%+4.6%B
Ahluwalia Contracts21,64069%+6.2%C
PSP Projects32,32064%+8.4%C
Local PMC consortium43,12058%+11.0%C
Renewal flag: cost variance > 5% AND on-time < 70% triggers automatic empanelment review.

S-37 · Photo evidence wall

EXIF GPS + last-photo-age
Tower A
Ulwe Pearl Phase II
19.040,72.8600d
Tower B
Ulwe Pearl Phase II
19.053,72.8713d
Tower C
Ulwe Pearl Phase II
19.066,72.8826d
Tower D
Ulwe Pearl Phase II
19.079,72.8939d
Tower E
Ulwe Pearl Phase II
19.092,72.90412d
Tower F
Ulwe Pearl Phase II
19.105,72.9151d
Tower A
Kharghar Sky Towers
19.118,72.9264d
Tower B
Kharghar Sky Towers
19.131,72.9377d
Tower C
Kharghar Sky Towers
19.144,72.94810d
Tower D
Kharghar Sky Towers
19.157,72.95913d
Tower A
Taloja Greens
19.170,72.9702d
Tower B
Taloja Greens
19.183,72.9815d
Tower C
Taloja Greens
19.196,72.9928d
Tower D
Taloja Greens
19.209,73.00311d
Tower E
Taloja Greens
19.222,73.0140d
Tower F
Taloja Greens
19.235,73.0253d
fresh ≤7d 8–29d stalled ≥30d